The project included the replacement of approximately 350 meters of water pipes, encompassing the main supply line and distribution pipes. Five new connection branches to the network were also created, along with a new fire hydrant and connection points.
Regarding sanitation, about 200 meters of new collectors were installed, along with nine inspection chambers and new branches and drains. Additionally, renovation and repair work was carried out on existing infrastructure.
The work also involved the necessary paving and restoration of the areas affected by the intervention. The total investment amounted to €76,471.56.
This initiative aims to renew essential infrastructure, improve network functionality, and enhance the quality and safety of services provided to the population of Peniche.