Ribeira Grande gains 52 new homes after recovery of Trás-Os-Mosteiros apartments

An investment by the Azores Government, under the PRR, breathes new life into abandoned apartments and boosts housing supply.

Ribeira Grande inaugura 52 novas habitações após recuperação de edifícios históricos

Câmara Municipal da Ribeira Grande

The city of Ribeira Grande now has 52 new homes, following the recovery of the Trás-Os-Mosteiros apartments, an investment by the Government of the Azores under the Recovery and Resilience Plan (PRR).

The president of the Ribeira Grande Municipal Council, Jaime Vieira, attended the handover ceremony for the 52 apartments in Trás-Os-Mosteiros. This significant investment by the Government of the Azores, under the Recovery and Resilience Plan (PRR), has revitalized a group of buildings that had been abandoned for years in the heart of the city.
Jaime Vieira welcomed the realization of this investment, emphasizing that it provides 52 families with decent housing, improving the living conditions of dozens of people and strengthening the housing dynamics of the municipality. Of the beneficiary families, thirteen come from other municipalities on the island of São Miguel, further enhancing Ribeira Grande's capacity to welcome new residents.
The Ribeira Grande Municipality also played a crucial role in this project, investing over half a million euros in essential infrastructure for the housing complex, including the basic sanitation network, access roads, common passage areas, and public lighting.
The municipal infrastructures vital for habitability are now operational. The domestic sewage network, the successfully tested water supply network, and the electrical and telecommunications networks were completed in August. The formal assignment of police numbers was concluded on September 29, 2026, and the Municipality is proceeding with the installation of water meters.
Fulfilling its commitment, the Municipal Council ensured the provision of essential infrastructure for connecting and using the homes, guaranteeing the necessary conditions for their occupation, even while exterior finishing work and urban landscaping of the parking areas are ongoing.
The effective occupation of several units, even before the official handover, demonstrated that habitability conditions were met. The absence of final paving on some roads did not prevent the practical use of the homes.
Currently, the project has an overall execution level of approximately 95%, with public lighting and pavement regularization work in the parking area nearing completion.
The recovery of the Trás-Os-Mosteiros apartments thus represents a significant step in the urban revitalization of Ribeira Grande, bringing life back to buildings that stood vacant for years and contributing to meeting housing needs through the requalification of existing heritage and the creation of new opportunities for families from the municipality and the island of São Miguel.
Based on information from the official source: Câmara Municipal da Ribeira Grande (21/11/2026)