The project, presented by E-REDES – Distribuição de Eletricidade, S.A., foresees the construction of a mixed high-voltage line operating at 60 kV, with an approximate extension of 1.34 kilometres. The infrastructure aims to establish the connection between the Fundão Substation and the Fundão BESS Substation. According to the descriptive memorandum, this work will allow the batteries to be charged from the electrical grid and subsequently inject the stored energy back into the grid.
In accordance with the notice issued by the Direção-Geral de Energia e Geologia (DGEG), the project documentation is available for consultation for 15 days, starting from the publication of the respective notice in the Diário da República. Consultation can be carried out at the Fundão Municipality Secretariat or at the DGEG DIEC Division, located at Rua Câmara Pestana, no. 74, 3030-163 Coimbra, during official hours.
During the same 15-day period, the public may submit complaints regarding the project approval. Complaints must be delivered to the Fundão Municipality Secretariat or the DGEG DIEC Division. Alternatively, they can be sent to the email address jose.toscano@dgeg.gov.pt. The Parish Council considers it important to ensure access to information regarding projects and interventions affecting the territory of the parishes.